13-Day Industrial Frisking Booth Construction at PepsiCo, Nalbari

SIE PROJECT DIARIES / CASE 001 / ASSAM

13 days.

From steel to sophistication.

Industrial frisking booth construction at the PepsiCo facility, Nalbari, Assam. Executed by SIE Engineering Construction under Semac.

Explore the build ↓

ACTUAL SITE PHOTOGRAPHS · REAL EXECUTION · 2026

Illuminated SIE industrial frisking booth interior at PepsiCo Nalbari
13 days
Delivery reported by SIE
433 sq. ft.
Nominal design footprint
11.5 × 3.5 m
Design dimensions
5 site films
Original site footage

01 / PROJECT OVERVIEW

Small footprint. Multiple disciplines.

At an industrial facility, even a compact utility structure must bring together function, construction coordination and architectural appearance. SIE executed this industrial frisking booth in Nalbari, combining MS fabrication, roofing, civil floor works, wall cladding, ceiling and lighting finishes. Delivered in 13 days, as reported by SIE, the project demonstrates the integration of multiple trades within a compact programme.

The dated site photographs show the progression from exposed steel posts to roofing and wall installation, followed by timber-tone panels and an illuminated passage. The following photographs show actual stages, not a digitally reconstructed finish.

BEFORE / Initial set-out — SIE industrial frisking booth construction, Nalbari
BEFORE / Initial set-out
Actual site photograph
AFTER / Architectural finish — SIE industrial frisking booth construction, Nalbari
AFTER / Architectural finish
Actual later-stage photograph

02 / INTERACTIVE FIELD JOURNAL

Follow the build.

Explore six visual chapters of the construction journey. Tap a stage to reveal the photograph and execution notes.

01 / The starting point — Initial set-out
The starting point — SIE industrial frisking booth construction, Nalbari
The starting point
Initial set-out

Steel base members were positioned to establish the passage footprint. The coordination drawings describe a perimeter frame and cross-ties.

02 / The structure rises — 28 September
The structure rises — SIE industrial frisking booth construction, Nalbari
The structure rises
28 September

Dated photographs document upright posts and the longitudinal steel frame. The exposed framework shows the progression of fabrication and erection.

03 / The roof takes shape — 30 September
The roof takes shape — SIE industrial frisking booth construction, Nalbari
The roof takes shape
30 September

A-type pitched steel trusses and longitudinal roof members define the structure. Daytime and evening images document the work.

04 / Roof and walls — 6 October
Roof and walls — SIE industrial frisking booth construction, Nalbari
Roof and walls
6 October

Profiled roofing sheets and wall framing were followed by backing-panel installation, visible in the same day’s evening photographs.

05 / Architectural finishing — Later stage
Architectural finishing — SIE industrial frisking booth construction, Nalbari
Architectural finishing
Later stage

Timber-tone vertical fluted panels, a finished ceiling, floor surface and integrated lighting create a refined passage.

06 / The illuminated result — 13-day delivery
The illuminated result — SIE industrial frisking booth construction, Nalbari
The illuminated result
13-day delivery

The later site photographs show the exterior and interior lighting. SIE reports delivery within 13 days; exact commencement and handover dates are not supplied.

13 days is SIE’s reported delivery duration. Photographic dates are not claimed as commencement or formal handover dates.

03 / SCOPE OF EXECUTION

One structure. Many skills.

01 / EXECUTION

MS fabrication

Steel base framing, posts, longitudinal members and pitched roof framework.

02 / EXECUTION

Civil floor works

Floor preparation and infill formed the passage base. Final material specifications require as-built confirmation.

03 / EXECUTION

Industrial roofing

Profiled roof sheets and edge trims form the weather-covering envelope.

04 / EXECUTION

Wall assembly

Backing panels and timber-tone vertical fluted cladding establish the architectural finish.

05 / EXECUTION

Ceiling and lighting

Finished linear ceiling and integrated lighting are visible in the later photographs.

06 / EXECUTION

Site coordination

Day and evening progress photographs record multiple construction trades within a compact programme.

04 / BLUEPRINT TO REALITY

Engineering before execution.

The original coordination drawing set dated 10 September 2026 describes a seven-stage proposed construction sequence: base frame, cross-ties, post erection, roof frame and covering, PCC floor infill, wall installation and final finishing. It also contains the A-type roof concept and proposed architectural elevation.

Design reference: the nominal 11.5 m × 3.5 m footprint corresponds to approximately 40.25 m² (433 sq. ft.). The drawings were issued for coordination, not for construction; member sizes, connections and final canopy geometry are not represented as verified as-built specifications.

View engineering coordination drawings (PDF) ↗

05 / ORIGINAL SITE FOOTAGE

Watch the work unfold.

Five actual project videos record the construction and finishing journey. Playback is optional, with no autoplay or automatic video preloading.

Site film 1 · SIE project archive
Site film 2 · SIE project archive
Site film 3 · SIE project archive
Site film 4 · SIE project archive
Site film 5 · SIE project archive

07 / BUILD WITH SIE

We don’t just show what we can build.
We show what we have built.

Planning an industrial utility structure, factory building, steel fabrication or civil construction project in Assam? Discuss the scope with SIE Engineering Construction.

Explore industrial construction → All services

SIE Engineering Construction · Guwahati, Assam · sieengineering.in

Industrial frisking booth construction: coordination lessons from the Nalbari project

The industrial frisking booth construction diary documents a compact industrial structure delivered under Semac at PepsiCo, Nalbari. The photographs and videos show the relationship between fabricated steel, civil floor works, roofing, enclosure, ceiling and lighting. The recorded 13-day milestone relates to this specific project; it is not a standard delivery promise for other installations.

For comparable industrial frisking booth construction, confirm the approved layout, clear opening requirements, access and circulation, structural connection details and the interfaces between the frame and enclosure before fabrication. Coordinate electrical points and service penetrations with the relevant trades so that completed finishes do not need avoidable rework.

When reviewing the programme, separate factory fabrication, transport, site readiness, erection, services and completion inspections. Confirm which work packages can overlap safely and which require acceptance by the client before the next trade starts. The Government of India construction safety manual resources are a useful reference alongside the site-specific safety plan and authorized work procedures.

For a new industrial frisking booth construction enquiry, prepare the location, proposed dimensions, intended use, enclosure requirements and photographs of the site. Review our industrial construction services and quotation comparison guide for help defining scope. Final design and execution requirements remain specific to the proposed facility.

industrial frisking booth construction: practical planning guide

Industrial frisking booth construction requires coordination between civil works, the steel framework, enclosure, electrical installations and operational access. Establish the footprint and available work area before detailing the frame. Check the approved door openings and equipment clearances before fabrication. The booth’s geometry and specifications must match the facility’s agreed requirements.

The documented industrial frisking booth construction at Nalbari illustrates a reported 13-day execution milestone. For a new booth, check interface dimensions, approved material specifications, installation access and site safety procedures. A separate record of civil and fabricated quantities supports measurement and billing. Industrial frisking booth construction should also allow for cleaning, maintenance and the intended movement of users through the space. Ask which elements are shop fabricated and which must be assembled at the site; this affects coordination and scheduling. The reported project duration should not be treated as a universal delivery commitment.

Related resources: industrial construction company in guwahati and our projects.

Industrial frisking booth: scope and interfaces

The industrial frisking booth project documentation shows the stages of fabrication, roofing, wall assembly and architectural finishing. A new industrial frisking booth needs the facility’s approved layout, operational requirements and clearances. Check the agreed specifications and the work sequence before committing to a fabrication programme.

Discuss your project with SIE Engineering

Speak directly with our team about 13-Day Industrial Frisking Booth Construction at PepsiCo, Nalbari.